Stainless Steel Pipe Work
For examples of some of the type of projects we have done in the past for Carbon Steel Pipe Work include but not limited to:
HAMILTON CITY COUNCIL WATER TREATMENT PLANT
SANDFILTER BACKWASH PUMP
Description of work;
- Fabricate & Install New Platforms, Stairs and Handrails
- Cut out concrete access opening and brace with support beam
- Shutdown main trunk line and tie in with new pipe work and isolation valve
- Install new pump on new concrete plinth
- Fabricate and install new 350NB carbon steel pipe work and supports
- Install new motor and drive shaft
HAMILTON CITY COUNCIL WASTEWATER TREATMENT PLANT
BIO-GAS SCRUBBER INSTALLATION AND PIPE WORK
Description of work;
- Project programming and management of sub-contractors.
- Installation of Bio-gas scrubber.
- Fabrication and installation of stainless-steel tubing, 50mm -150mm.
- Fabrication and installation of carbon steel pipe work, 50NB.
- Design, build and install pipe bridges and pipe layouts.
- Installation of pumps and blowers.
HAMILTON CITY COUNCIL WASTEWATER TREATMENT PLANT
CO-GEN INSTALLATION AND PIPE WORK
Description of work;
- Design and build of project and management of sub-contractors.
- Installation of CAT V20 gas engine.
- Fabrication and installation of carbon steel pipe work, 150NB-400NB.
- Fabrication and installation of stainless-steel pipe work, 50NB-400NB.
- Installation of Heat exchanger and radiator.
HAMILTON CITY COUNCIL WATER TREATMENT PLANT
LOW LIFT PUMPS UPGRADE
Description of work;
- Project programming and management of sub-contractors.
- Cutting into main plant feed pipes and fit isolation valves.
- Fabrication and installation of carbon steel pipe work, 300NB–600NB.
- Installation of submersible pumps.